A Tauranga hotelier is pleased the council has agreed to put a loading bay outside his hotel but is frustrated by their lack of action.
In January, Local Democracy Reporting shared Quest Tauranga Central director Craig Mckenzie's concerns about needing a loading bay.
The footpath outside his Devonport Road hotel has become and unofficial loading zone for courier drivers and the occasional hotel guest.
One of the guests was fined for stopping on the footpath and hotel staff were 'accused” of telling guests to park on the footpath by parking wardens, says Mckenzie.
After conversations with Tauranga City Council (TCC) it was agreed a loading bay was needed, which Mckenzie says is great.
Four months later and the hotelier is still waiting to hear back from council about when the loading bay will be installed.
On January 27, Mckenzie received an email from one of the council's senior transport engineers, with a sketch of the proposed loading bay and was told he would get a call the following week.
Mckenzie says he did not get that call and has sent further emails asking for an update but has not had a reply.
'It started with a hiss and roar. ‘Here's some plans and we'll get into it,' and then complete radio silence. Emails, messages, he doesn't respond,” he says.
Asked what he thought of the time taken to install the loading bay Mckenzie replied: I don't know their [the council's] priorities and I know there's a lot of work they're doing, so I'm not one to cast stones.”
'But to me it seems a ridiculous amount of time for what looks like a small job. For something that will help businesses out in the street, which businesses are struggling.”
Where the loading bay is going is also a concern for the hotelier, it will be placed directly on the road.
Mckenzie is worried cars could turn out in front of a large delivery truck blindly into oncoming traffic.
The linen delivery truck has permission to stop on the road until a loading bay is installed but Craig Mckenzie said this was dangerous. Photo: Supplied.
The hotel also receives three linen deliveries a week and the large truck offloads heavy cages of linen which could fall into traffic, he says.
The council advised him the truck could stop on the road out front until the loading bay was installed.
When the linen truck stopped on the road, motorists were tooting their horns and pulling out from behind it blindly, says Mckenzie.
They now get the truck to nudge into the start of their narrow driveway instead of parking partly on the footpath like it did previously.
He has suggested to council using some of the footpath for the loading zone because he believes it is wide enough to cater for both pedestrians and vehicles.
'There's still so much room on the footpath and it doesn't cause any grief. I think officiating what's currently being used would make a difference.”
Mckenzie says vehicles use the area between six to 12 times a day.
Responding to Mckenzie's concerns TCC director of transport Brendan Bisley says they planned to install the loading bay this week, but the rain meant that had not been possible.
"The road needs to be dry to paint the line markings, so we are keeping a close eye on the forecast for our next clear day to install the loading bay,” he says.
In terms of the timeframe, Bisley says there were 'various processes” that needed to happen before installation.
The bylaw must first be updated around the use of the loading zone which was then approved by council, he says.
'Once the bylaw has been updated and approved, the work gets scheduled with contractors.
"The contracting team have a significant amount of work on their plates and with this project being weather dependent, the timing for the installation has unfortunately been postponed,” says Bisley.
The council approved the bylaw change for the loading bay at a meeting in March.
With placement of the loading zone, Bisley says council had 'carefully considered” all options including the suggestion of using the footpath.
'Our concern with using part of the footpath for the loading bay is pedestrians not being aware of trucks reversing and the limited visibility truck drivers have manoeuvring into that space.
'After taking all of this into account, we believe the safest option is to keep the loading bay on the road.
'Truck drivers go through health and safety training and must actively manage risks around them when loading and unloading goods, our biggest concern is for pedestrians and maintaining the full footpath is important to mitigate those pedestrian safety risks.”
Asked about not hearing back from a transport engineer, Bisley responded: 'Council staff have shared the loading zone plans with the hotel manager and have also had phone conversations outlining why it will not be possible to install the loading zone across the footpath.
'While a decision has been made to install the loading zone on the road, we would welcome a meeting to discuss the various risks and concerns which were factored into our decision.”
Bisley says the estimated cost of the loading bay would be $1000.
Public Interest Journalism funded through NZ On Air
3 comments
Loading bay - Devonport Rd
Posted on 12-05-2023 19:28 | By tia
Trucks parking on this road is one of the biggest issues facing Tauranga and Council seem hell bent on allowing it. Why do they not instruct business to let delivery companies know that they must use rear service lanes which are surely designed to keep deliveries off main thoroughfares?
It's a hotel
Posted on 13-05-2023 13:26 | By Kancho
Hotels and apartments and businesses often don't have sufficient service lanes and not are customer entrance as in this case . Giving tickets to someone checking into or out of a hotel as in a his case is anti visitors / tourist. No wonder people in don't want to go there. Council dictates building and street layout so obviously inadequate then that's in council planning. Generally minor inconvenience for trucks trying to get through the day
Loading Bay delays
Posted on 15-05-2023 06:55 | By rally4life
This is not the only small project facing lengthy delays. Try getting a section of footpath repaid across a commercial driveway. Up to two years wait now!
Leave a Comment
You must be logged in to make a comment.